CASE STUDY

FULL ROAD AND ROUNDABOUT RECONSTRUCTION

  • Site: A603 London Road – Biggleswade
  • Client: Walker Construction

Full Road and Roundabout Reconstruction consisting of existing road realignment and new roundabouts. 10000m2 of full depth construction carried out over day and night visits, followed on by 20000m2 of plane out and relay carried out over nightime road closures, Challenging site due to TM restrictions, but over 240ts of hot rolled asphalt and pre coated chippings laid per shift at night.

  • 3000m2 of full depth machine laid footpath surfacing to Bedfordshire Highway specification.

Suppliers:

  • Aggregate Industries
  • Cemex
  • PD Stonham
  • Sims Milling Services
  • Connor Construction